Routing setup checklist ​

Goal ​

Ready process masters before BOM activation and WO release policies that require a routing.

Who it is for ​

Planner / admin.

Preconditions ​

  • Work centers created for costing cells.
  • Optional: Manufacturing setup → Routing operation types catalog (labels for planning; WO engine uses minutes/rates from the routing snapshot).

Steps ​

  1. Map the shop process into sequenced operations.
  2. Attach work centers and setup/run minutes.
  3. In Manufacturing setup → Options, decide Require routing on WO release (default off).
  4. Link the routing on each relevant BOM before activating.

Result ​

Routings are available for BOMs; release policy can enforce them.